Permitted: Pre-construction requirements for all confinement feeding operations that use
unformed manure storage and operations with 1,000 animal units or more that use
formed manure storage.
A construction permit and manure management plan are required for new construction, modifications and expansions.
Owners must apply for a construction permit application at least 60 days prior to start of construction. Producers should allow an extra 18 days for mailing and for the county to file an appeal. If the county appeals the permit application, it could take as long as 120 days before construction can start. For permitting requirements, see the following:
|