As roads approach a stream crossing, proper road drainage is critical
to avoid sedimentation in streams. Three common stream crossing
structures are culverts, bridges and fords.
Stream crossings must be designed, constructed and maintained to
safely handle expected vehicle loads and to minimize disturbance
of streambanks, channels and, ultimately, aquatic organisms.
Consider streambed material, stream size, storm frequency, flow
rates, intensity of use (permanent or temporary) and the passage
of fish when planning crossings. The USDA Natural Resources
Conservation Service (NRCS), or a private consultant can help with
designing fords and culverts. To design a bridge, contact
a private consultant or experienced contractor
BMPs for Stream Crossings Use soil stabilization practices on exposed
soil at stream crossings. Use seed and mulch and install temporary
sediment control structures such as straw bales or silt fences immediately
following construction to minimize erosion into streams. Maintain
these practices until the soil is permanently stabilized.
Please refer to the section about soil stabilization, below.
- Design, construct and maintain stream crossings to avoid disrupting
the migration or movement of fish and other aquatic life.Bridges
or arch culverts that retain the natural stream bottom and slope
are preferred for this reason.
- Install stream crossings using materials that are clean, non-erodible
and non-toxic to aquatic life.
- Install stream crossing structures at right angles to the stream
channel.
- Minimize channel changes and the amount of excavation or fill
needed at the crossing.
- Limit construction activity in the water to periods of low or
normal flow. Keep use of the equipment in the stream to
a minimum.
- Construct a bridge or place the fill over a culvert higher than
the road approach to prevent surface road runoff from draining
onto the crossing structure and into the stream (Figure C-1).
Figure C-1. Place fill directly over a culvert
higher than the road approach to prevent surface road runoff from
draining onto the crossing structure and into the stream. (Adapted
from Wisconsin Department of Natural Resources, 1995.)
- Stabilize approaches to bridge, culvert and ford crossing with
aggregate or other suitable material to reduce sediment entering
the stream.
- Anchor temporary structures on one end with a cable or other
device so they do not float away during high water.Install them
so they can be easily removedwhen no longer used, regardless of
the season.
- Avoid areas with riffles and pool complexes, wetlands,
mudflates or vegetatedshallows which are
considered special aquatic sites under the Clean Waters
Act (CWA), Section 404 and have strict requirements for permits.
Divert road drainage into undisturbed vegetation, preferably outside
the SMA so that the drainage does not directly enter the stream
(Figure C-2) Also refer to Diversion Structures on page 50.
Figure C-2. Diversion ditch. (Adapted from Wisconsin Department
of Natural Resources, 1995.)
Pipe Culverts for Stream Crossings · Install pipe culverts
long enough so that road fill does not extend beyond the ends of
a culvert.
Install permanent culverts that are large enough to pass flood flows
and are a minimum of 12 inches in diameter. Culverts that
are too small can plug up with debris and result in the road washing
out or in flooding upstream.
Iowa law states that the landowner and/or contractor
are responsible to obtain a flood easement from any affected property
owners upstream of culvert crossing that are not designed to pass
the 100-year flood.
The USDA Natural Resources Conservation Service, or a private engineering
consultant can help with sizing culverts.
Figure C-3. Install culverts so there is no change in the stream bottom
elevation. (Adapted from Wisconsin Department of Natural Resources,
1995.)
Install culverts so there is no change in the stream bottom elevation
(Figure C-3). Culverts should not cause damming or pooling.
Firmly pack fill material around culverts, particularly around the
bottom half. Cover the top of culverts with fill to a depth
of one-third of the pipe diameter or at least 12 inches, whichever
is greater, to prevent crushing (Figure C-4).
Figure C- 4. Installation of culverts. (Adapted from Montana
Department of State Lands, 1992.
Use riprap around the inlet of culverts to prevent water from eroding
and undercutting the culvert (Figure C-5a and 5b). For permanent
installations, use filter fabric under the riprap. In addition,
consider using flared culvert end sections for inlets.
Keep culverts clear and free of debris so that water can pass unimpeded
at all times. This is especially important in areas where beaver
are present.
Figure C-5a. Use riprap around the inlet of culverts.
Figure C-5b. Use geotextile filter fabric for permanent installations.
(Adapted from Wisconsin Department of Natural Resources, 1995.)
Fords
Use fords for crossing dry streambeds or where fording would cause
minimal water quality impacts.
Locate fords where streambanks are low.
Streambed should have a firm rock or gravel base. Otherwise,
install stabilizing material such as reinforced concrete planks,
crushed rock, riprap or rubber mats on streambeds.
Road Construction and Drainage - BMPs
The most effective method to control erosion on woodland roads is
to keep water from accumulating on the road surface. Fast-moving
water can easily erode soil from road surfaces and ditches, but
road erosion can be controlled when water drains off the road surface
and is dispersed into vegetation and ground litter.
Design and construct roads to remove water from road surface to
keep the road dry and structurally sound. Figure C-6 shows
three common road designs: crowned, outsloped and insloped.
Install insloped roads with ditches and adequate cross drainage.
Outsloped roads (usually outsloped 2-4%) are less expensive to construct
and maintain; use them on roads with moderate gradients and stable
soils.
Figure C-6. Typical road designs form drainage
and stability. (Adapted from Wisconsin Department of Natural Resources,
1995.)
Construct stable cut-and-fill slopes that will revegetate easily,
either naturally or artificially.
Do not bury debris in the road base. It causes uneven settling
that can led to erosion and frost-heaving that creates mud
holes.
Compact the road base material or allow it to settle before using
the road. This will reduce the amount of water that soaks
into it, increasing the road’s carrying capacity, reducing road
maintenance and reducing erosion.
Face the road with gravel where steep grades, erodible soils or
high traffic volume make the potential for surface erosion significant.
Locate gravel pits outside SMAs, using proper location, development
and soil stabilization
practices
to minimize erosion from the pits.
Drainage Structures - BMPs
Road-drainage structures include cross drains (pipe culverts, open-top
culverts, broad-base dips and water bars) and water-diversion structures.
Cross drains allow water from roadside ditches to move from one
side of the road to the other.
Where necessary to protect water quality, install road drainage
structures to remove storm water or seepage from the road surface
and ditches. Space these structure at intervals close enough
to minimize waterflow volume and speed, avoiding ditch erosion.
As road grades increase, use drainage structures more often.
See Table C- 1 below.
Provide erosion protection for outflows from road drainage structure
to minimize erosion and disperse the water, allowing it to soak
into the soil. Riprap, mulch and/or seeding may be necessary.
Please refer to the section on soil stabilization.
Table C- 1. Recommended distances between drainage
structures on woodland roads and skid trails.
Road grade% Distance betweenwaterbars (feet) Distance
between broad-based dips and cross-drain culverts (feet).
|
1
|
400
|
500
|
|
2
|
250
|
300
|
|
5
|
130
|
180
|
|
10
|
80
|
150
|
|
15
|
50
|
130
|
|
25+
|
40
|
110
|
Figure C-7. Cross-drain culvert. (Adapted from
Wisconsin Department of Natural Resources, 1995.)
Pipe Culverts for Cross Drains
Install pipe culverts to provide cross drainage on roads grades
at regular intervals immediately above steep grades, below bank
seepage and where water will run onto log landings or woodland roads.
Install pipe culverts long enough so that road fill does not extend
beyond the end of a culvert.
Install cross drain pipe culverts at grades at least 2% more than
the ditch grade and angled 30 to 45 degrees to improve inlet efficiency
(Figure C-7).
Select the size of cross-drain culverts according to the size of
the road and area drained by the ditch. To avoid clogging,
permanent culverts should be at least 12 inches in diameter.
The USDA Natural Resources Conservation Services or a private engineering
consultant can help with sizing culverts.
Install pipe culverts on a surface of compacted granular material.
Firmly pack fill material around culverts, particularly around the
bottom half. Cover the top of the culvert with fill to a depth
of one-third of the pipe diameter, or at least 12 inches (whichever
is greater) to prevent crushing (Figure C-4).
Use riprap around the inlet of culverts to prevent water from eroding
and undercutting the culvert.
Open-Top Culverts
Open-top culverts provide cross drainage and road surface drainage
(Figure C-8) and are usually installed on seasonal or temporary
roads.
Figure C-8. Open-top log culvert. (Adapted
from Wisconsin Department of Natural Resources, 1995.)
Install open-top culverts to provide cross drainage immediately
above steep grades, below bank seepage, where water will run onto
log landings or woodland roads and on road grades at regular intervals.
Clean open-top culverts frequently since they easily fill in with
debris.
Broad-Based Dips
Broad-based dips can provide cross drainage and road-surface drainage
for roads and skid trails with a gradient of 15% or less (Figure
C-9). Broad-based dips can be used instead of culverts, usually
at lower cost and with lower maintenance. Dips are not used
for draining seeps, or for intermittent or permanent streams.
Construct broad-based dips deep enough to provide adequate drainage
and wide enough to
allow trucks
and equipment to pass safely.
Place a surface of crushed stone or gravel on the dip and mound
for soils and conditions where rutting may occur.
Figure C-9. Broad-based dip. (Adapted
from Wisconsin Department of Natural Resources, 1995.)
Water Bars
A water bar is a shallow trench with a mound (or
berm) which provides cross drainage and intercepts runoff from skid
trails, recreational trails, firebreaks, or inactive or closed roads.
(Figure C-10). Constructing a water bar will minimize erosion
and provide conditions for natural or artificial revegetation.
Place water bars at a 30 to 45 degree angle with a cross drainage
grade of 2%.
Figure C-10. Water bar. (Adapted from Wisconsin Department
of Natural Resources, 1995.)
Diversion Structures
Diversion ditches, or berms, divert water away from
roads and side ditches and channel it into vegetation (Figure C-2).
These structures are often used before stream crossings to ensure
that water will be diverted into vegetation and not directly into
a stream, lake or wetland.
Construct diversion ditches so they intersect the
roadside ditch at the same depth and are turned down slope 1% to
3% (Figure C-2)
Soil Stabilization - BMPs
Soil stabilization practices are used where soil
is exposed and natural revegetation is inadequate (i.e., road development,
skid trails and landings) to prevent soil erosion and subsequent
sedimentation into streams, lakes and wetlands. This occurs
during roads construction and when the road system is active or
inactive. Practices include mulching, seeding and installing
sediment control structures.
It is always more efficient and cost effective to prevent erosion
than it is to repair damage after the fact.
Mulching and Seeding
Use mulch and/or seed where necessary to minimize soil erosion.
Mulch, such as straw, woodchips or bark, retains
soil moisture - important for seed germination and protects the
soil surface from erosion due to runoff and raindrop impact.
Mulch can be used to: (1) promote natural revegetation
or (2) protect seeds that have been spread over an area. If
you seed, apply mulch immediately afterward. Netting may be
necessary to hold mulch in place on steep slopes or on areas where
water flow concentrates.
Seed mixtures should include fast growing species
for quick soil protection plus perennial species for longer soil
protection until native vegetation returns to the site. Recommendations
for seed mixes that are best for specific regions in Iowa are available
from your District IDNR Forester, Wildlife Biologist or USDA Natural
Resources Conservation Service office.
A suggested minimum generic seed mixture, applied at the rate of
55 lbs./acre, is as follows:
White Dutch clover 10 lbs./acre
Perennial rye grass 10 lbs./acre
Annual rye grass 20 lbs./acre
Creeping red fescue 15 lbs./acre
Table C-2 is provided to assist you in determining
the area (acres) of a specified length and width of road surface.
Table C-2. Road Surface Area Determination
(acres)
Road Length
Road Width
(ft)
8’ 10’
12’ 14’
18’ 20’
50
.01 .01
.01 .02
.02 .02
100
.022 .02
.03 .03
.04 .05
250
05 .06
.07 .08
.10 .11
500
.09 .12
.14 .16
.21 .23
750
.144 .17
.21 .24
.31 .34
1000
.18 .24
.28 .32
.41 .46
1500
.28 .34
.41 .48
.62 .69
2000
.36 .48
.56 .64
.83 .92
5000
.92 1.15
1.38 1.61
2.07 2.30
5280
.97 1.21
1.45 1.70
2.18 2.43
Sediment Control Structures
Install sediment control structures where necessary to slow the
flow of runoff and to trap sediment until vegetation is established
at the sediment source. Sediment control structures include
straw bale fencing, silt fencing and sediment traps (Figures C-11).
Maintain, clean, or replace sediment-control structure until areas
of exposed soil are stabilized.
Figure C-11a. Straw bale fencing to slow runoff and trap sediment
for sheet flow and channelized flow. (Adapted from Wisconsin
Department of Natural Resources, 1995.)
Figure C-11b. Silt fencing to slow runoff and
trap sediment for sheet flow, not channelized flow. (Adapted
from Wisconsin Department of Natural Resources, 1995.)
Figure C-11c. A sediment trap to slow runoff and trap sediment for
channelized flow. (Adapted from Wisconsin Department of Natural
Resources, 1995.)
Road Maintenance
Roads must be well maintained or water quality protection structures
may quickly degrade. For both active and inactive roads, follow
BMPs in the Soil Stabilization section on pages 34-36.
Active Roads
Inspect the road system at regular intervals, especially after
heavy rainfall, to detect problems and to schedule repairs.
Clear debris from culverts, ditches, dips and other drainage structures
to decrease clogging that can lead to washouts. Place the
debris where it cannot be washed back into these structures or into
open water.
Keep traffic to a minimum during wet periods and spring breakup
to reduce maintenance needs.
Shape road surfaces periodically to maintain proper surface drainage.
Fill in ruts and holes with gravel or compacted fill as soon as
possible to reduce erosion potential.
Remove berms along the edge of the road if they will trap water
on the road.
When dust control agents are used, apply them in a manner that
will keep these compounds from entering lakes, streams and groundwater.
Consult a qualified road engineer from the County Highway Commissioner’s
office or Iowa Department of ransportation for assistance in selecting
the appropriate chemicals and amounts.
Note: It is illegal to spread oil on road,land or water in Iowa.
Inactive Roads
When woodland roads are inactive for extended periods,
closing the system will help to protect the road surface and the
water quality protection structures. Consider erecting a barrier
to traffic such a gate or berm and post “Closed” signs at the entrance
of temporarily closed roads. Stating the length of time and/or
reason for closure and inviting acceptable uses may be helpful to
assure compliance.
Remove all temporary drainage and stream crossing structures.
Shape all road system surfaces to maintain proper surface drainage,
if necessary.
Install water bars where necessary. Please refer to the section
on water bars and follow recommendations in Table C- 1.
Inspect and maintain road surfaces, permanent drainage and streamcrossing
structures (ditches, culverts, bridges, etc.) to minimize erosion.
Federal Requirements for Woodland Roads in Wetlands
The following 15 BMPs must be implemented in order
to qualify for the silvicultural exemption from a federal section
404 permit when building a temporary or permanent road or skid trail
in a wetland (33 CFR part 323.4). The silvicultural exemption
is only applicable when the primary purpose of the roads is for
normal silvicultural purposes. This listing is an attempt
to explain the 15 BMPs in lay language. The exact language
of the law may be obtained by contacting the Army Corps of Engineers.
1. Limit the number, length and width of roads and
skid trails to the minimum necessary to accomplish
the landowner’s objective.
2. Locate roads outside streamside management areas
except at stream crossings. Formore
information, please refer to the section on Streamside Management
Areas.
3. Road fill must be bridged, culverted, or otherwise
designed to prevent restriction ofexpected
flood flows.
4. Properly stabilize and maintain road fill during
and after road construction to prevent erosion.
5. While building a road with fill material, minimize the use of
road construction equipment in the wetland area.
6. Minimize disturbance of vegetation while designing,
constructing and maintaining roads.
7. Correctly design, construct and maintain wetland
road crossings to avoid disrupting the migration
or movement of fish and other aquatic life.
8. Use fill from upland sources whenever feasible.
9. Place fill in a way that does not take or jeopardize the continued
existence of athreatened or endangered species (as defined under
the Endangered Species Act or adversely modify or destroy the critical
habitat of such species.
10. Avoid placing fill in breeding and nesting areas
for migratory waterfowl, in spawning areas
and in wetlands if practical alternatives exist.
11. Fill shall not be placed near a public water supply intake.
12. Fill shall not be placed in areas of concentrated shellfish
production.
13. Fill shall not be placed in waterbodies or on land regarded
as part of the National Wildand Scenic River System.
14. Use fill free from toxic pollutants.
15. Completely remove all temporary fills and restore
the area to its original elevation.
Table of Contents
|